Works are set to commence on pedestrian level crossings in Wellington this week as part of the NSW Government’s rail infrastructure program.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
The first phase of works come after representatives from John Holland Rail (JHR), Dubbo Regional Council, NSW TrainLink, GrainCorp and Michael White attended an on-site meeting in July 2017 where they discussed legal access requirements at the station and at the silos along the corridor.
Works – valued at $160,000 – will be completed by TfNSW’s contractor, JHR, who will install new concrete surfaces on the Gobolion Street and Whiteley Street pedestrian level crossings to improve the surface for pedestrians.
“New approach footpaths are being installed and a new surface laid across the railway track at a total cost of $160,000,” a spokesperson for JHR said.
“The work will also include safety improvements with a new pedestrian maze and signage installed.”
The 24-hour work will take place at the pedestrian level crossings from today, January 17 to Tuesday, January 23, with most of the night works taking place from January 19 to 22.
A statement released by JHR advises the work will be conducted in both day and night shifts to minimise disruption to rail and pedestrian traffic.
Residents may also hear construction noise during site operations and see some extra vehicle and heavy machinery movement in the area.
- John Holland spokesperson
It also states crossings will be closed while the works are being completed, with temporary diversions in place at Gobolion Street and Whiteley Street where pedestrians will be diverted to the existing Gisborne Street crossing, or the temporary crossing near the Gobolion Street works.
“We will endeavor to minimise the impact to the community wherever possible, during the works,” the release read.
“Residents may also hear construction noise during site operations and see some extra vehicle and heavy machinery movement in the area.”
“Thank you for your patience as we complete this essential work on the Country Regional Network.”
Further works are planned in the overall effort to reduce trespassing in the rail corridor.
“The footbridge design is still being finalised and timing on the replacement is still being considered,” the spokesperson said.
JHR anticipates the fencing element will begin prior to June 2018.
For further enquiries contact the community relations team on 1300 661 390.
Read more: Bridge fix, fences for rail line